Case story
Expansion of synthesis production at existing synthesis factory F2
Project at Lundbeck A/S Lumsås where the existing process plant in synthesis factory F2 was upgraded with a new synthesis unit consisting of a reactor source, a reactor and a condenser. In connection with the upgrade the new synthesis unit had to be supplied with panels for managing valves and general control of the sources, the reactor and the condenser.
Competencies
Project phases
The process
Lundbeck was responsible for the overall project management, HAZOP, mechanical installation of components as well as for qualification of the new process equipment. Process Engineering reported to the project manager from Lundbeck and provided consulting services on process and electricity/SRO in relation to the process plant, the electricity supply and CE marking. In addition, we prepared an ATEX report about the entire installation.
In order to streamline the process, and in partnership with Lundbeck, we focused on how the tests performed during qualification could be integrated in the CE marking.
Service and scope of the project
- Design of supply current
- SRO design
- Tender material and requirements specification
- Installation tender
- Installation and construction management
- Start-up engineer(s)
- ATEX report of the entire installation
- Documentation and CE marking
Do you have a project for which you need strong engineering skills?
Contact us and learn how we can assist you as your consulting engineering partner